MAN Subsea Compression Trains Hit 50,000 Hours

Premium Content

December 14, 2018

MAN Energy Solutions’ first subsea compression trains at Equinor’s Åsgard field have achieved 50,000 operating hours with nearly 100% availability.

Åsgard became the world’s first subsea gas compression facility to operate 984 ft. (300 m) below sea level in 2015. The operation features two HOFIM motor-compressor units from MAN Energy Solutions Switzerland Ltd.

“In the early days we just had a few valves on the sea floor,” said Roald Sirevaag, chief engineer subsea technology of Equinor. “Now there’s almost a complete factory down there.”

By placing compression on the sea floor, the operator gains improved energy efficiency, MAN said. Compressors that operate closer to the well produce higher efficiency and production rates.

The subsea technology also contributes to improvements in recovery rates and gas field longevity. By the end of 2015, analyses indicated that the pressure in Åsgard’s reservoirs would have been too low to ensure stable flows and production, MAN said. The MAN units help extend the reservoirs’ productive life for another 15 years. Overall, around 282 million barrels of oil equivalent will be added, MAN said.

Latest News
U.S. natural gas production hits record in July
Permian growth and expanding takeaway capacity pushed gross withdrawals
GPA Midstream honors industry leaders and volunteers at 2026 convention
Awards presented in San Antonio recognized lifetime achievement, technical contributions, committee leadership and service to the midstream industry
PETROS, Höegh Evi to develop Kuching LNG terminal
Proposed Sarawak project would use an FSRU to supply natural gas for power generation and other regional energy needs
CONNECT WITH THE TEAM
Jack Burke Senior Editor Tel: +1 262 527 0815 E-mail: [email protected]
Kristin Pride Brand Manager – North America/European Sales Executive Tel: +1 720 298 8546 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA