Startup milestone positions QatarEnergy–ExxonMobil joint venture for initial exports in second quarter 2026

With first LNG production achieved, Golden Pass LNG is on track to commence exports to global markets in the second quarter of 2026. (Image: Golden Pass LNG)

Golden Pass LNG, a joint venture between QatarEnergy and ExxonMobil, has produced its first liquefied natural gas (LNG) from Train 1 at its Sabine Pass terminal, marking a key step toward full commercial operations.

The milestone follows several years of engineering, permitting, construction and commissioning work at the Texas Gulf Coast facility, one of the largest LNG export projects under development in the United States.

“Today, we began producing LNG at our terminal in Sabine Pass, marking the completion of a significant effort to construct, commission and start up the first LNG Train and the beginning of operating a world-class facility with an exceptional team,” said Alex Savva, president and CEO of Golden Pass LNG.

First LNG production represents a critical transition from construction to operations, enabling the project to move toward its first cargo and sustained liquefaction output.

Golden Pass said the startup of Train 1 will support the ramp-up to commercial operations, with initial LNG exports expected in the second quarter of 2026. The facility is designed to supply LNG to global markets amid continued growth in international demand.

“I’m proud of our team and their tireless work to ensure we safely reached this milestone,” said Jeremy Horn, vice president of operations. “We’re excited to go to work delivering Texas LNG to power the world.”

Once fully operational, the Sabine Pass terminal is expected to contribute significant liquefaction capacity to the global market, reinforcing the U.S. position as a leading LNG exporter.

The Train 1 milestone marks the beginning of phased startup activities across the facility, as Golden Pass progresses toward full operational capability and long-term commercial delivery commitments.

Latest News
Global Compression Services adds two executives to leadership team
Gary Killingsworth named Gulf Coast regional sales manager; Christy Hanson Stafford appointed vice president of human resources
FERC to consider 265,750-hp Mountain Valley Pipeline expansion
Proposed MVP Boost Project would add compression at three existing West Virginia stations and construct a new compressor station in Virginia, increasing natural gas transportation capacity by 600,000 Dth/d
Caterpillar expands 3600 engine production as gas compression demand grows
Winston-Salem facility will provide additional assembly and testing capacity as company targets nearly tripling large reciprocating engine production capacity by 2030
CONNECT WITH THE TEAM
Jack Burke Senior Editor Tel: +1 262 527 0815 E-mail: [email protected]
Kristin Pride Brand Manager – North America/European Sales Executive Tel: +1 720 298 8546 E-mail: [email protected]
CONNECT WITH SOCIAL MEDIA