Kinder Morgan has ordered two of Everest Sciences Corp.’s ECOChill units for its Uniondale Compresssor station on the Tennessee Gas Pipeline near West Clifford, Pennsylvania.

The hybrid turbine inlet units will provide filtered and chilled inlet air to a Solar Taurus 70 turbine and a Centaur 40 turbine that drive compressors, enabling them to operate at consistent winter-like capacity during warm weather days.

Everest said when ambient air temperature rises, gas turbine output decreases, reducing the horsepower available to push natural gas through the pipeline. It said the other options for cooling turbine inlet air, the mechanical chilling or direct evaporative methods, have higher energy costs or are not as effective.

An ECOChill installation at a southern Wyoming pipeline station has enabled consistent inlet air temperatures between 45° and 55°F (7.2° and 12.7°C), increasing horsepower over the summer months (COMPRESSORtech2, Jan.-Feb. 2014, p. 16). Other Everest Sciences installations serve gas processing and natural gas liquids facilities in Texas.

Edit ModuleShow Tags

Archive »Archive »

Answer: Past Tense - January/February 2017

Past Tense - January/February 2017

Ariel Compressors To Power Two Miami CNG Stations

Love’s Trillium CNG has received a 10-year, more than US$330 million contract to build two public-access compressed natural gas (CNG) fueling stations for the Miami-Dade Transit in southern Florida.

GMRC Call For Papers

FERC Approves Seven Projects Before No-Quorum Period

The Federal Energy Regulatory Commission (FERC) certified seven projects at the start of the month in anticipation of entering into a no-quorum period, according to the U.S. Energy Information Administration (EIA).